⚠️ Most of I-14 is still being planned piece by piece. TxDOT's published schedule shows land purchases on US 83 north of Menard starting in 2027. Do not sign a survey form or an offer without an independent review.
Interstate 14 · Texas · About 1,035 miles

Interstate 14 Is Coming Across Texas.
Here Is Every Route, Where TxDOT Is Moving First, and What It Means for Land Along It.

Got a TxDOT letter or a survey request? Call or text (469) 484-7960Status checked October 27, 2026 against TxDOT's own records

I-14 runs from West Texas to the Louisiana line along highways that already exist, mostly US 190. Only about 25 miles, Copperas Cove to Belton, carry the I-14 signs today. Every other piece becomes interstate when TxDOT upgrades it: wider lanes, frontage roads, overpasses, and in a few places a new road around a town. Those upgrades are when land gets bought. Below: every I-14 route on one map, the TxDOT jobs already scheduled along each one, and what a highway taking leaves out of a first offer.

1,035
Miles on TxDOT's I-14 map
25
Miles signed I-14 today
35
TxDOT upgrade jobs along the routes
Mar 2027
Earliest expected bid
On this pageI-14 mapCheck your addressEvery routeWhat it costsThe offerFAQFree review by a senior consultant

Almost every condemnation case is a fight about a number, not about the law.

Our documented results

Almost every condemnation case is a fight about a number, not about the law.

Utility easement · Houston, TX
$16,000→$138,000 +762%
Damages their team missed.
Utility easement · Irving, TX
$12,000→$50,000 +317%
Damages their team missed.
Highway · Grand Parkway (SH 99), Chambers County, TX
$2.5M→$5M +100%
The agency’s appraisal left value out.
Highway · I‑35 expansion, McLennan County, TX
$20,000→$385,000 +1,825%
Their number missed value on the take.

Text us the letter

A photo of the offer is enough — a senior consultant reads it and tells you what we see.

Text (469) 484-7960 →

Four documented matters, each traced from the original offer letter to final settlement — two utility easements and two highway condemnations, labelled on each. Not an average and not a prediction; when we look at yours and think the number is close to right, we tell you so. National ROW is a right-of-way consulting firm, not a law firm, and nothing here is legal advice.

I-14 in Texas — status

Last verified October 27, 2026
Future interstate — upgraded piece by piece
What it isInterstate 14, the Central Texas Corridor / Gulf Coast Strategic Highway
Set in law byFAST Act (2015) and the Infrastructure Investment and Jobs Act (2021), which named the I-14 system and added its Texas legs
Who builds itTexas Department of Transportation (TxDOT), district by district
Length on TxDOT's mapAbout 1,035 miles across 31 counties (measured from TxDOT's Future Interstates lines)
Signed I-14 todayAbout 25 miles, Copperas Cove to Belton
TxDOT upgrade jobs on these routes35 jobs of $8 million or more in Project Tracker, listed route by route below
Earliest expected bidMar 2027
Land parcels on TxDOT's right-of-way mapNo parcels being bought yet on the I-14 jobs listed here (34 already bought on jobs that are finished or under construction), as of October 27, 2026
Routes still being chosenRogers to Huntsville (TxDOT Central Texas corridor study, 17 options, none chosen)
TxDOT statewide pageI-14 System in Texas

Also searched as: Interstate 14 Texas route, I-14 map, Future I-14, Central Texas Corridor, Gulf Coast Strategic Highway, US 190 interstate upgrade.

Download the I-14 route map

A one-page map of every I-14 route in Texas, with the mileage of each one, drawn from TxDOT's own Future Interstates data. Print it, take it to your appraisal district, or send it to whoever is advising you.

Map of every Interstate 14 route in Texas from TxDOT's Future Interstates data: signed I-14 from Copperas Cove to Belton, the main line along US 190 from Brady to the Sabine River, I-14 North through San Angelo to Midland and Odessa, I-14 South from I-10 in Pecos County, and the US 83, US 69, US 96 and FM 305/US 385 spurs, with miles for each

Download the I-14 route map

Is your property near an I-14 route?

Enter an address to see roughly how far it sits from the nearest I-14 route on TxDOT's map, and which route that is.

Signed I-14 today Main I-14 (Leg C) I-14 North (Leg A) I-14 South (Leg B) US 83 spur (Leg D) US 69 spur (Leg E) US 96 spur (Leg F) FM 305 / US 385 spur (Leg G) Your location
Route lines come from TxDOT's Future Interstates map, as of October 27, 2026. They follow today's highways; where TxDOT builds a frontage road, an interchange or a relief route, the land it needs can sit to either side or away from the line. This tool is an approximation, not a survey and not legal advice. Distances are straight-line estimates. Addresses you type are sent to the U.S. Census Bureau's public geocoder to find coordinates. If we find a match, we drop the address and county into the review form lower down so you do not have to retype them — nothing reaches National ROW unless you actually submit that form.

Call or text us directly — we answer owners same day.

(469) 484-7960

info@nationalrow.com

Free review — I-14 Texas

Tell us about your property. A senior consultant reads every one of these and calls you within the hour, 8am–6pm Central, Monday to Friday. Outside those hours, first thing the next morning.

By submitting this form, you agree that National ROW may contact you by phone, text message (SMS), and email at the number and address provided — including by automated means — about your inquiry. Consent is not a condition of any service. Message and data rates may apply. Message frequency may vary. Reply STOP to opt out of texts, HELP for help. See our Privacy Policy.
No obligation · Zero out of pocket · Private · We'll never sell your info

National ROW is a right-of-way consulting firm, not a law firm. No attorney-client relationship is created by submitting this form. Results vary by case. Prior results do not guarantee similar outcomes.

We've got it from here.

Your case is in review. A senior consultant reads everything you shared and calls you within the hour, 8am–6pm Central, Monday to Friday. Outside those hours, first thing the next morning.

In the meantime, don't sign anything and don't feel pressured to respond to their representatives.

Need to talk now? Call or text  (469) 484-7960

Every I-14 route in Texas, and where each one stands

TxDOT's map splits I-14 into the signed piece, the main line, a north and a south branch, and four spurs. For each one: where it runs, the counties it crosses, and every TxDOT upgrade job of $8 million or more that runs along it, pulled from TxDOT's Project Tracker on October 27, 2026.

Find your route below and tap it to open.

Signed I-14 today · Copperas Cove to Belton · 25 mi

About 25 miles of US 190, from Copperas Cove to I-35 in Belton, already carry the I-14 signs. TxDOT still has work planned on this piece, listed below. Jobs that have already been bid are past the land-buying stage, because TxDOT buys the land it needs before a job goes out to bid.

Counties on TxDOT's line: Bell (22.2 mi), Coryell (2.7 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0231-04-060
IH 14 · Bell County
FM 2410 IN W BELTON to IH 35
WIDEN FROM FOUR TO SIX LANES AND RESURFACE
Bid / under way$40.2M
0231-02-067
IH 14 · Coryell County
US 190 to 0.15 MI E of Clark Rd
Widen Road - Add Lanes
Bid / under way$11.3M
0231-04-064
IH 14 · Bell County
IH 14 to IH 35
Interchange Improvement (New Or Update)
Bid Jan 2035$141.9M

Main I-14 (Leg C) · Brady to the Louisiana line · 389 mi

The main line follows US 190 east from Brady through Lampasas County, Copperas Cove, Killeen, Belton and Temple, past Rogers and Cameron toward Bryan–College Station, then on through Huntsville, Livingston, Woodville and Jasper, and finally SH 63 to the Sabine River at Burr's Ferry. TxDOT's map also routes it over short pieces of US 183, I-35, US 77, US 79 and I-45.

Where it is moving first: the I-14 Extension, Segment 1 on I-35 between Belton and Temple (TxDOT job 0015-14-109; Project Tracker estimate $601.3M, bid expected Jan 2031). TxDOT showed a revised layout at public meetings on August 5 and 6, 2026. Segment 3, SH 95 in Temple to Rogers, is planned as frontage roads and overpasses, with bids TxDOT expects in 2036 and 2037. Around Rogers, the US 190 widening and relief route was bid in 2019, so that land has already been bought. From Rogers to Huntsville, TxDOT's Central Texas corridor study has 17 possible routes and has not chosen one. At the Louisiana line, the SH 63 Sabine River bridge at Burr's Ferry has its environmental approval (November 13, 2025), with construction expected in 2027.

Counties on TxDOT's line: Lampasas (44.6 mi), Milam (43.2 mi), Polk (38.3 mi), San Saba (33.2 mi), Walker (31.8 mi), Madison (29.3 mi), Tyler (25.6 mi), Brazos (22.8 mi), Newton (22.7 mi), Bell (22.3 mi), Jasper (21.4 mi), McCulloch (18 mi), Robertson (17.5 mi), San Jacinto (12.6 mi), Coryell (5.2 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0185-01-030
US 190 · Bell County
2.0 MI S OF FM 436 IN HEIDENHEIMER to MILAM C/L
WIDEN FROM TWO TO FOUR LANE DIVIDED HIGHWAY
Bid / under way$64.6M
0675-05-105
IH 45 · Madison County
0.5 Mi S of SS 104 to US 190
New Arterial
Bid Aug 2027$93.1M
0015-14-109
IH 35 · Bell County
US 190 IN BELTON to S LP 363 IN TEMPLE
Widen Road - Add Lanes
Bid Jan 2031$601.3M
0015-14-133
IH 35 · Bell County
WB US 190 to SB IH 35
Interchange Improvement (New Or Update)
Bid Jan 2033$49.4M
0185-05-004
US 190 · Bell County
0.3 Mi N of N190J to FM 93
Highway Improvement
Bid Jan 2036$41.9M
0320-01-075
US 190 · Bell County
SP 290 to SL 363
Highway Improvement
Bid Jan 2037$174.4M
0049-12-124
US 190 · Brazos County
BS-6R NORTH to SH 21
Construct New Road
Bid Sep 2039$75.0M

I-14 North (Leg A) · Odessa and Midland to Brady, through San Angelo · 211 mi

I-14 North starts on I-20 at Odessa and runs to Midland, then follows SH 158 to Sterling City and US 87 through San Angelo to US 190 at Brady.

Counties on TxDOT's line: Tom Green (51.3 mi), Concho (34.6 mi), Midland (32.8 mi), Glasscock (31.5 mi), Sterling (29.8 mi), McCulloch (17.4 mi), Ector (8.6 mi), Coke (4.4 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0005-14-093
IH 20 · Midland County
ECTOR COUNTY LINE to EAST OF CR 1300
Widen Road - Add Lanes
Bid / under way$146.9M
0005-14-094
IH 20 · Midland County
EAST OF CR 1300 to EAST OF CR 1250
Widen Road - Add Lanes
Bid / under way$174.1M
0005-14-092
IH 20 · Midland County
EAST OF CR 1250 to EAST OF SH 349
Widen Road - Add Lanes
Bid Mar 2027$222.5M
0005-13-063
IH 20 · Ector County
MONAHANS DRAW to EAST OF JBS PARKWAY
Widen Road - Add Lanes
Bid Jan 2029$249.0M
0069-07-110
US 87 · Tom Green County
AT FM 2105 to .
Highway Improvement
Bid Jan 2032$18.0M
0070-02-094
US 87 · Tom Green County
AT SL 306 AND FM 1223 to .
Highway Improvement
Bid Jan 2032$30.0M
0070-02-092
US 87 · Tom Green County
US 277 to SL 306 and FM 1223
Highway Improvement
Bid Jul 2032$27.5M
0005-15-093
IH 20 · Midland County
EAST OF SH 349 to EAST OF FM 1208
Widen Road - Add Lanes
Bid Jan 2033$516.0M

I-14 South (Leg B) · I-10 in Pecos County to Brady · 177 mi

I-14 South follows US 190 from I-10 in Pecos County, near Iraan, east through Eldorado and Menard to Brady, where it meets the main line.

Counties on TxDOT's line: Crockett (55.6 mi), Schleicher (51.8 mi), Menard (33.2 mi), McCulloch (21.1 mi), Pecos (15.4 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0396-03-028
US 190 · Schleicher County
US 277 to Menard County Line
Highway Improvement
Bid Apr 2029$36.2M
0396-05-022
US 190 · Menard County
Schleicher County Line to US 83
Highway Improvement
Bid Apr 2031$28.4M

US 83 spur (Leg D) · Eden to I-10 at Junction · 51 mi

US 83 from Eden to I-10 at Junction. TxDOT held a public hearing in Menard on September 29, 2026, and its schedule shows land purchases starting in 2027. Full details, map and owner FAQ for US 83 →

Counties on TxDOT's line: Menard (27.2 mi), Kimble (14.5 mi), Concho (9.2 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0035-05-059
US 83 · Menard County
Concho County Line to US 190 North of Menard
Highway Improvement
Bid Jan 2028$84.1M
0035-06-033
US 83 · Menard County
SH 29 to KIMBLE COUNTY LINE
Highway Improvement
Bid Feb 2029$43.1M
0035-07-045
US 83 · Kimble County
Menard County Line to IH 10
Highway Improvement
Bid Mar 2030$58.9M

US 69 spur (Leg E) · Beaumont to Woodville · 54 mi

US 69 from I-10 in Beaumont north to US 190 near Woodville.

Counties on TxDOT's line: Hardin (28.1 mi), Tyler (18.6 mi), Jefferson (7.1 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0200-11-095
US 69 · Jefferson County
LNVA CANAL, SOUTH to IH 10
WIDEN FREEWAY FROM 4 TO 6 LANES
Bid / under way$25.7M
0065-07-062
US 69 · Jefferson County
TRAM ROAD, SOUTH to LNVA CANAL
WIDEN FREEWAY FROM 4 TO 6 LANES
Bid / under way$21.1M
0200-08-049
US 69 · Tyler County
0.1 MI SOUTH OF BLACK CREEK to HARDIN COUNTY LINE
Widen Road - Add Lanes
Bid / under way$87.3M
0200-09-069
US 69 · Hardin County
TYLER COUNTY LINE to 0.75 MI SOUTH OF FM 1003
Widen Road - Add Lanes
Bid / under way$66.1M
0065-07-065
US 69 · Jefferson County
HARDIN C/L, SOUTH to TRAM ROAD
Construct New Road
Bid Nov 2027$32.4M
0065-06-067
US 69 · Hardin County
US 96, SOUTH to JEFFERSON C/L
Construct New Road
Bid Nov 2027$46.5M
0200-07-043
US 69 · Tyler County
1.5 MI NORTH OF US 190 to FM 1013
Construct New Road
Bid May 2035$142.4M
0200-08-050
US 69 · Tyler County
FM 1013 to 1 MI SOUTH OF BLACK CREEK
Construct New Road
Bid May 2035$116.0M
0200-10-060
US 69 · Hardin County
0.75 MI S OF FM 1003 to MITCHELL ROAD
Construct Frontage Roads
Bid May 2035$450.0M
0200-10-072
US 69 · Hardin County
SH 327, SOUTH to N OF WEST WALTON
Construct New Road
Bid Aug 2040$8.0M

US 96 spur (Leg F) · Beaumont to Jasper · 58 mi

US 96 from I-10 in Beaumont north to US 190 near Jasper.

Counties on TxDOT's line: Jasper (44.1 mi), Hardin (13.7 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0065-05-123
US 96 · Hardin County
US 69 (1.0 MI N OF FM 421) to US 96 NEAR VILLAGE CREEK
New Arterial
Bid Aug 2040$12.0M

FM 305 / US 385 spur (Leg G) · I-10 in Pecos County to Odessa · 71 mi

The connection from I-10 in Pecos County north to Odessa, along US 190, FM 305 through McCamey and US 385 through Crane.

Counties on TxDOT's line: Crane (32.6 mi), Ector (12.7 mi), Upton (10.3 mi), Pecos (8.6 mi), Crockett (6.8 mi).

TxDOT jobs along this route

TxDOT jobWhere / whatStatusEst. cost
0229-04-057
US 385 · Upton County
CRANE COUNTY LINE to NIMITZ STREET IN MCCAMEY
Highway Improvement
Bid / under way$42.1M

A job appears here when at least 60% of its length, or at least a mile of it, runs within about 800 feet of an I-14 line on TxDOT's map. Bid dates are TxDOT's estimates and move often. Smaller maintenance work such as resurfacing is left out because it rarely takes land.

Is your land on one of these routes?

Send us the TxDOT letter, the plat, or just your county and the nearest crossroads. We will tell you which project it is, where TxDOT is in the process, and what that means for you.

Free review by a senior consultant →

Or call or text (469) 484-7960 — a senior consultant answers owners the same day.

Why I-14 is being built

I-14 was created to tie Central Texas, and the large Army post at Killeen, to the Gulf Coast ports and to the interstates running east into Louisiana, Mississippi, Alabama and Georgia. TxDOT describes it as a strategic link between the military forts of the southern states and the ports used to ship equipment out. It is also meant to carry the freight and growth along the US 190 corridor, which today is a mix of four-lane highway, two-lane country road and town main streets.

Congress set the corridor in federal law in 2015 and added the North, South and spur legs in 2021. Federal designation does not build anything. It tells TxDOT that when a piece of US 190, US 83, US 87, US 69 or US 96 is rebuilt, it should be rebuilt to interstate standards: divided lanes, controlled access, frontage roads and grade-separated crossings. That is why I-14 shows up as many separate TxDOT jobs rather than one project, and why it will arrive in different places years or decades apart.

TxDOT published an I-14 System in Texas plan in 2024 after listening sessions with communities along the route. It says the exact routing in many places still has to be worked out with local governments, which is why some sections, such as Rogers to Huntsville, are still being studied.

What happens on an I-14 project, in order

Every piece of I-14 goes through the same TxDOT steps. Here is the sequence, and where your leverage sits in it.

Tap any step to see what happens.

Where the leverage actually is: most of it sits between the appraisal and the final offer. Once you sign a deed to TxDOT, the sale is done. The cheapest hour you will ever spend is the one before you sign anything.

What an I-14 taking costs a landowner

A highway taking is usually not an easement. TxDOT normally buys the land outright, and the strip becomes part of the road for good. That is very different from a pipeline or power line, where you keep the land under an easement.

The strip is rarely the whole loss

On most I-14 pieces the road is being widened along today's highway, so what TxDOT takes is frontage: the front of a ranch, a home site, a store's parking lot, a sign, a well, a fence line. The price of that strip per acre is usually the easiest number in the offer. The harder ones are what the taking does to everything you keep.

Access changes when a road becomes an interstate

An interstate controls access. Where TxDOT builds an I-14 main lane, driveways and gates stop opening straight onto it, and traffic moves to frontage roads, turnarounds and interchanges. In Texas, a loss of access is compensable only in some situations, so it has to be documented carefully, with how the property actually works before and after.

Frontage land and land near interchanges

Land along an interstate frontage road or near a new interchange can be worth more after the project, not less. TxDOT's appraisal is supposed to value the land you lose as it was before the project, without the bump the project itself creates, and the land you keep as it is after. Getting those two sides right is where offers on highway projects most often go wrong in both directions.

Where the money actually is

In almost every highway case the biggest items besides the land are damage to the remainder, the cost to cure (moving a fence, a gate, a well, a sign, a septic system or a parking layout so the property works again) and, for businesses, the effect on visibility and access. Those are the items a first offer most often leaves thin.

Want to know what your property is actually worth on this route?

A senior consultant will walk your numbers with you: the land TxDOT needs, what it does to the rest of your property, and the value a first offer tends to leave out. No cost and no obligation.

Free review by a senior consultant →

Or call or text (469) 484-7960 — a senior consultant answers owners the same day.

What the offer will look like — and what it usually leaves out

When TxDOT's offer arrives it will not say "here is our opening bid." It comes as a package: a cover letter, the appraisal or a summary of it, a right-of-way map of the part TxDOT wants, and the Landowner's Bill of Rights.

The three numbers every offer package contains

ComponentWhat it pays forTypically
Value of the part acquiredThe strip itself, priced against comparable salesLargest single line
Damages to the remainderLost value to everything you keep — shape, access, frontage, use, marketabilityFrequently understated
Cost to cureWhat it costs to fix what the taking broke — fences, gates, wells, signs, driveways, parkingFrequently omitted

How much does the back half matter? In one recent Texas highway offer package our team reviewed, damages to the remainder made up about 39% of the total offer and cost to cure another 29%. Nearly seven of every ten dollars came from something other than the raw land price. If your offer is almost all a per-acre land number with little for damages and cure, that is not because your property has none. It is because nobody quantified them.

How to read your own package in ten minutes. Find the total. Find the per-acre or per-square-foot figure and the area it is applied to. Multiply. Whatever is left over is what they are paying for damages and cure. If that leftover is small or zero, you have found your issue.

What their offer may miss on an I-14 project

TxDOT's appraiser works for TxDOT. That does not make them dishonest — it makes them the other side's expert. These are the items that most often come in low or not at all.

Tap each one to see what it means on your property.

Damage to the Remainder

A narrower lot, a house closer to the traffic, a ranch with a new corner cut off. What the land you keep is worth after the project is a separate number from the strip.

Access and Driveways

Where a gate or driveway moves to a frontage road, a turnaround or a new crossing, how the property works changes. It has to be documented before and after.

Signs, Parking and Layout

For a business, the loss of a sign, parking spaces or a truck turning area can cost far more than the land under it.

Wells, Septic and Utilities

A water well, septic field, propane tank or power service inside the strip has to be replaced or moved, and that cost belongs in the offer.

Fences, Gates and Pens

Miles of new fence, cattle guards, gates and pens near the road are a cost to cure, not a favor.

Split Tracts

Where a new road or relief route cuts across a tract, the pieces on each side can each be worth less than their share of the whole.

Development Potential

Land that could have been divided, built on or sold as frontage has a value beyond its farm or ranch use. A taking that ends that potential is compensable.

Temporary Construction Easements

Room TxDOT uses only during construction has its own value, for the time it is actually used.

Already holding a TxDOT offer letter?

Send it over with the appraisal if they gave you one — a photo of the pages is enough. A senior consultant will tell you what we see.

Free review by a senior consultant →

Or call or text (469) 484-7960 — a senior consultant answers owners the same day.

How we work — no upfront cost

We are on the owner's side of the right-of-way. We are paid out of the increase, which means we do not get paid unless you do better.

01

Free review by a senior consultant

Send us whatever they sent you — a survey permission form, a letter, an appraisal, an offer. We read it and show you what it does and does not account for. No charge, no obligation.

02

Independent appraisal

We bring in independent, certified appraisers to value the part acquired and, critically, to document damages to the remainder and cost to cure.

03

We negotiate

We deal with the land agents and their appraisers directly, with documentation behind every number, so you are not negotiating alone against people who do this full time.

04

You get paid more

Our fee is a percentage of the increase above the original offer. If we do not improve it, you owe us nothing.

To be clear about what we are: National ROW is a right-of-way consulting firm. We are not a law firm and we do not give legal advice. Much of what a landowner needs in this process is valuation and negotiation work rather than litigation — that is what we do. When a case needs a lawyer, we say so and we coordinate with condemnation counsel.

Questions landowners along I-14 are asking

Tap any question to see the answer.

Is I-14 approved?

Congress made the route a future interstate in 2015 and added more legs in 2021, so the corridor is set in federal law. But there is no single approval for the whole thing. Each piece becomes interstate when TxDOT upgrades it, and every upgrade is its own project with its own environmental review and public hearing. As of October 27, 2026, only about 25 miles, Copperas Cove to Belton, are signed as I-14.

Will my land be taken for I-14?

Only if it sits where TxDOT upgrades a piece of the route. Most of I-14 follows highways that already exist, so the usual taking is a strip along your frontage for wider lanes, frontage roads or an interchange. A few places may get a road on new ground, such as a relief route around a town or the Rogers-to-Huntsville section TxDOT is still studying. Being near the line on this page does not mean you will be contacted.

When will TxDOT start buying land?

TxDOT buys land before it puts a job out to bid, usually one to three years ahead. Of the I-14 jobs on this page, the earliest bid TxDOT expects is Mar 2027. On US 83 north of Menard, TxDOT's own schedule shows land purchases from 2027 to 2029. As of October 27, 2026, TxDOT's public right-of-way parcel map shows no parcels being bought yet on the I-14 jobs listed here.

How do I find out which I-14 project my land is on?

Use the address check on this page, or look at the letter TxDOT sent you. It will name the highway and usually a job number in the form 0000-00-000, called a CSJ. Send us the letter and we will match it to the project and tell you where it stands.

Do I have to let TxDOT survey my land?

TxDOT will often ask to survey before it makes an offer. What you are asked to sign matters, so read it before you agree and ask what the crew will do, where and for how long. If you are not sure what you are being asked to sign, send it to us first. It costs nothing to check.

Do I have to accept TxDOT's offer?

No. Texas law requires TxDOT to make a written initial offer, give you the Landowner's Bill of Rights, and wait at least 30 days before a final offer, which must be at least the amount of its own written appraisal. You then have at least 14 days to respond. Those offers are TxDOT's opening position, not the last word on what your land is worth.

What happens if we cannot agree on a price?

TxDOT can file a condemnation case. A judge appoints three local landowners as special commissioners, who hold a hearing and decide the amount. Either side can object to their award and take the case to court. Most cases settle well before that point.

Is National ROW a law firm?

No. National ROW is a right-of-way and condemnation consulting firm, and we represent property owners only, never the agency. We do the valuation and negotiation work. When a case needs a lawyer, we say so and coordinate with condemnation counsel.

What does it cost to have you look at my offer?

The review is free. If you engage us, we work on contingency: our fee is a percentage of the increase above the original offer. If we do not improve it, you owe us nothing.

Where can I read TxDOT's own documents?

TxDOT's I-14 System in Texas page has the statewide map and plan. Each project's job number links to TxDOT's Project Tracker in the tables above, and the sources at the bottom of this page link every document we used.

Send us what they sent you.

A TxDOT letter, survey request, appraisal or offer — whatever stage you are at, we will read it and tell you where it is weak. Free, and there is no obligation to go further.

Free review by a senior consultant →

Or call or text (469) 484-7960 — we answer owners the same day.

Sources

  1. Texas Department of Transportation — I-14 System in Texas (statewide map, implementation plan, fact sheet).
  2. TxDOT — Future Interstates map data (I-14 lines used for the map and mileage on this page), TxDOT Open Data.
  3. TxDOT — Project Tracker (job numbers, estimated bid dates and costs in the route tables), pulled October 27, 2026.
  4. TxDOT — right-of-way parcel map (ROW_ODP_Proposed_Parcels), TxDOT Open Data, checked October 27, 2026.
  5. TxDOT — I-14 Central Texas Corridor Study (Rogers to Huntsville).
  6. TxDOT — US 83 widening in Menard County, public hearing September 29, 2026.
  7. TxDOT — I-14 Extension, SH 95 in Temple to BU 190 in Rogers, public meeting July 11, 2024.
  8. U.S. Congress — Infrastructure Investment and Jobs Act (2021), I-14 designations.
  9. U.S. Census Bureau — TIGERweb county boundaries (county mileage).
  10. Texas Landowner’s Bill of Rights — Office of the Texas Attorney General.

Mileage and county figures on this page were measured from TxDOT's own Future Interstates lines against Census county boundaries. TxDOT job details come straight from Project Tracker and are refreshed whenever this page is rebuilt. Bid dates are TxDOT estimates and change often.