I-14 Segment 1 · I-35 · Belton to Temple

TxDOT Is Rebuilding I-35 From Belton to Temple for I-14.
The Road Strip Grows to About 470 Feet. Here Is What It Means for Owners Along It.

Got a TxDOT letter or a survey request? Call or text (469) 484-7960Status checked October 27, 2026 against TxDOT's own records

I-14 will be extended from Belton to Rogers in three pieces. Segment 1 is the first: about 8 miles of I-35 from south of Loop 121 in Belton to Loop 363 in Temple, with new interstate interchanges and a flyover. TxDOT's plan adds lanes and frontage-road changes along a road lined with homes and businesses, and its August 2026 timeline starts land buying in late 2027. Below: where the project runs, what changed in August, the TxDOT jobs involved, and what a first offer on a highway taking usually leaves out.

~8
Miles of I-35 in Segment 1
470 ft
Typical road strip (TxDOT, Aug 2026)
Late 2027
Land buying begins (TxDOT timeline)
$601.3M
Project Tracker estimate, main job
On this pageProject mapCheck your addressWhat changedTxDOT jobsThe offerFAQFree review by a senior consultant

Almost every condemnation case is a fight about a number, not about the law.

Our documented results

Almost every condemnation case is a fight about a number, not about the law.

Utility easement · Houston, TX
$16,000→$138,000 +762%
Damages their team missed.
Utility easement · Irving, TX
$12,000→$50,000 +317%
Damages their team missed.
Highway · Grand Parkway (SH 99), Chambers County, TX
$2.5M→$5M +100%
The agency’s appraisal left value out.
Highway · I‑35 expansion, McLennan County, TX
$20,000→$385,000 +1,825%
Their number missed value on the take.

Text us the letter

A photo of the offer is enough — a senior consultant reads it and tells you what we see.

Text (469) 484-7960 →

Four documented matters, each traced from the original offer letter to final settlement — two utility easements and two highway condemnations, labelled on each. Not an average and not a prediction; when we look at yours and think the number is close to right, we tell you so. National ROW is a right-of-way consulting firm, not a law firm, and nothing here is legal advice.

I-14 Segment 1 — status

Last verified October 27, 2026
Third public meeting held — land buying planned from late 2027
Official nameI-14 Extension: I-35 from south of Loop 121 in Belton to Loop 363/US 190/SH 36 in Temple (Segment 1)
AgencyTexas Department of Transportation, Waco District
Main TxDOT job (CSJ)0015-14-109, plus 5 related I-35 and interchange jobs listed below
CountyBell
LengthAbout 8 miles (TxDOT August 2026 notice)
What gets builtFour general lanes each way (one more than today), two non-tolled express lanes each way, two to three frontage-road lanes, a shared-use path, rebuilt I-14/US 190/I-35 interchanges and a flyover to Loop 363
Typical road stripAbout 470 feet (cut from about 500 feet after the January 2026 meetings)
Public meetingsMay 2024, January 2026, August 5–6, 2026 (comments closed August 21, 2026)
Land purchases (TxDOT timeline)Begin late 2027 after environmental clearance, continuing into summer 2028
Construction (TxDOT timeline)2031, depending on environmental clearance and funding
Project Tracker estimate$601.3M for the main job, bid expected Jan 2031
Land parcels on TxDOT's right-of-way mapNone being bought yet, as of October 27, 2026
TxDOT Waco District(254) 867-2700  ·  100 South Loop Dr., Waco

Also searched as: I-14 Segment 1, I-14 extension Belton Temple, I-35 widening Belton to Temple, I-35 Loop 363 flyover, I-14 I-35 interchange Belton.

Download the Segment 1 project map

A one-page map of Segment 1 and the related I-35 jobs, with TxDOT's widths and schedule, drawn from TxDOT's own project data. Print it, take it to your appraisal district, or send it to whoever is advising you.

Map of TxDOT's I-14 Segment 1 project on I-35 from south of Loop 121 in Belton to Loop 363 in Temple, Bell County, with related interchange jobs and TxDOT's schedule

Download the Segment 1 map

Segment 1 is one piece of Interstate 14. See every I-14 route in Texas, and the TxDOT jobs scheduled on each.

Is your property on Segment 1?

Enter an address to see roughly how far it sits from the center of I-35 in the Segment 1 project.

Segment 1 (0015-14-109) Related I-35 and interchange jobs Rest of I-14 on TxDOT's map Your location
Project lines come from TxDOT's Project Tracker, as of October 27, 2026. The line is the center of today's road; the proposed strip is about 470 feet wide in most places and wider at interchanges. Confirm your block on TxDOT's roll plots. This tool is an approximation, not a survey and not legal advice. Addresses you type are sent to the U.S. Census Bureau's public geocoder to find coordinates. If we find a match, we drop the address and county into the review form lower down so you do not have to retype them — nothing reaches National ROW unless you actually submit that form.

Call or text us directly — we answer owners same day.

(469) 484-7960

info@nationalrow.com

Free review — I-14 Segment 1 (I-35 Belton-Temple)

Tell us about your property. A senior consultant reads every one of these and calls you within the hour, 8am–6pm Central, Monday to Friday. Outside those hours, first thing the next morning.

By submitting this form, you agree that National ROW may contact you by phone, text message (SMS), and email at the number and address provided — including by automated means — about your inquiry. Consent is not a condition of any service. Message and data rates may apply. Message frequency may vary. Reply STOP to opt out of texts, HELP for help. See our Privacy Policy.
No obligation · Zero out of pocket · Private · We'll never sell your info

National ROW is a right-of-way consulting firm, not a law firm. No attorney-client relationship is created by submitting this form. Results vary by case. Prior results do not guarantee similar outcomes.

We've got it from here.

Your case is in review. A senior consultant reads everything you shared and calls you within the hour, 8am–6pm Central, Monday to Friday. Outside those hours, first thing the next morning.

In the meantime, don't sign anything and don't feel pressured to respond to their representatives.

Need to talk now? Call or text  (469) 484-7960

What changed at the August 2026 meetings

TxDOT held its third round of Segment 1 meetings in Temple on August 5 and Belton on August 6, 2026. It said the changes came from what owners and the community raised in January.

January 2026 designAugust 2026 design
Express lanesSix (three each way)Four (two each way)
Typical road stripAbout 500 feetAbout 470 feet
Land needed—About 26 acres less, nearly 15% (TxDOT estimate)
Flyover to Loop 363Higher design speed, wider curveLower design speed, tighter curve, fewer neighborhood impacts
A smaller strip is still a taking. If TxDOT's drawings show your property inside the new line, the August changes may shrink what TxDOT wants, but they do not change how it will be valued, or what a first offer tends to leave out.

The TxDOT jobs on this stretch of I-35

Segment 1 is TxDOT job 0015-14-109. These related I-35 and interchange jobs sit on the same stretch. All figures are from TxDOT's Project Tracker on October 27, 2026; bid dates are estimates and move often.

TxDOT jobWhere / whatStatusEst. cost
0015-14-109US 190 IN BELTON to S LP 363 IN TEMPLE
Widen Road - Add Lanes
Bid Jan 2031$601.3M
0015-06-0881.16 Miles South of SL 121 to US 190
Widen Road - Add Lanes
Bid Jan 2031$90.7M
0015-14-133WB US 190 to SB IH 35
Interchange Improvement (New Or Update)
Bid Jan 2033$49.4M
0015-14-134NB IH 35 to EB US 190
Interchange Improvement (New Or Update)
Bid Jan 2033$40.4M
0231-04-064IH 14 to IH 35
Interchange Improvement (New Or Update)
Bid Jan 2035$141.9M
0015-14-136US 190 IN BELTON to S SL 363 IN TEMPLE
Widen Road - Add Lanes And Shoulders
Bid Jan 2036$74.7M

After Segment 1: Temple to Rogers

Segment 2 follows Loop 363 around Temple and is still in early planning. Segment 3 runs from SH 95 in Temple to BU 190 in Rogers, planned as frontage roads and overpasses along US 190. TxDOT's Segment 3 jobs in Project Tracker:

TxDOT jobWhere / whatStatusEst. cost
0185-01-040
US 190 · Bell County
SL 363 to .3 MI N N190J
Highway Improvement
Bid Jan 2037$37.6M
0185-01-044
US 190 · Bell County
S190J to Rogers Bypass
Highway Improvement
Bid Jan 2037$153.1M
0185-05-001
US 190 · Bell County
FM 93 to S190J
Highway Improvement
Bid Jan 2037$61.2M
0185-05-004
US 190 · Bell County
0.3 Mi N of N190J to FM 93
Highway Improvement
Bid Jan 2036$41.9M
0320-01-075
US 190 · Bell County
SP 290 to SL 363
Highway Improvement
Bid Jan 2037$174.4M

Is your property along I-35 between Belton and Temple?

Send us the TxDOT letter, the plat, or just your address. We will tell you where your property sits against the project and what happens next.

Free review by a senior consultant →

Or call or text (469) 484-7960 — a senior consultant answers owners the same day.

What happens next on Segment 1, in order

Tap any step to see what happens.

Where the leverage actually is: most of it sits between the appraisal and the final offer. Once you sign a deed to TxDOT, the sale is done. The cheapest hour you will ever spend is the one before you sign anything.

What the offer will look like — and what it usually leaves out

When TxDOT's offer arrives it comes as a package: a cover letter, the appraisal or a summary of it, a right-of-way map of the part TxDOT wants, and the Landowner's Bill of Rights.

ComponentWhat it pays forTypically
Value of the part acquiredThe strip itself, priced against comparable salesLargest single line
Damages to the remainderLost value to everything you keep — shape, access, frontage, visibility, useFrequently understated
Cost to cureWhat it costs to fix what the taking broke — signs, parking, driveways, utilities, fencesFrequently omitted

How much does the back half matter? In one recent Texas highway offer package our team reviewed, damages to the remainder made up about 39% of the total offer and cost to cure another 29%. Nearly seven of every ten dollars came from something other than the raw land price.

How to read your own package in ten minutes. Find the total. Find the per-acre or per-square-foot figure and the area it is applied to. Multiply. Whatever is left over is what they are paying for damages and cure. If that leftover is small or zero, you have found your issue.

What their offer may miss on Segment 1

TxDOT's appraiser works for TxDOT. That does not make them dishonest — it makes them the other side's expert. These are the items that most often come in low or not at all on an urban interstate widening.

Tap each one to see what it means on your property.

Damage to the Remainder

A shallower lot, a building closer to the frontage road, a parcel that no longer fits its best use. What you keep is worth something different afterward.

Parking and Circulation

Losing even a row of parking or a truck turning area can make a business site work worse than the square footage suggests.

Signs and Visibility

A pylon sign that has to move, or a new wall or flyover that blocks the view from I-35, has real value to a business.

Driveways and Access

Driveways that close, move or become right-in, right-out change how customers reach you. Document how the site works today.

Utilities and Improvements

Water, sewer, power, fences, landscaping and paving inside the strip have to be replaced or moved, and that belongs in the offer.

Temporary Construction Easements

Room TxDOT uses only during construction has its own value, for the time it is actually used.

Already holding a TxDOT letter or offer?

Send it over with the appraisal if they gave you one — a photo of the pages is enough. A senior consultant will tell you what we see.

Free review by a senior consultant →

Or call or text (469) 484-7960 — a senior consultant answers owners the same day.

How we work — no upfront cost

We are on the owner's side of the right-of-way. We are paid out of the increase, which means we do not get paid unless you do better.

01

Free review by a senior consultant

Send us whatever they sent you — a survey permission form, a letter, an appraisal, an offer. We read it and show you what it does and does not account for. No charge, no obligation.

02

Independent appraisal

We bring in independent, certified appraisers to value the part acquired and, critically, to document damages to the remainder and cost to cure.

03

We negotiate

We deal with the land agents and their appraisers directly, with documentation behind every number, so you are not negotiating alone against people who do this full time.

04

You get paid more

Our fee is a percentage of the increase above the original offer. If we do not improve it, you owe us nothing.

To be clear about what we are: National ROW is a right-of-way consulting firm. We are not a law firm and we do not give legal advice. Much of what a landowner needs in this process is valuation and negotiation work rather than litigation — that is what we do. When a case needs a lawyer, we say so and we coordinate with condemnation counsel.

Questions owners along Segment 1 are asking

Tap any question to see the answer.

What is I-14 Segment 1?

It is the first of three pieces that carry I-14 from Belton to Rogers. Segment 1 rebuilds about 8 miles of I-35 from south of Loop 121 in Belton to Loop 363, US 190 and SH 36 in Temple, including the I-14, US 190 and I-35 interchanges. I-14 will run along I-35 here, so this I-35 widening is also the I-14 extension.

Will TxDOT need my land?

Very possibly, if you are along I-35 between Belton and Temple. TxDOT's August 2026 schematic shows a typical road strip of about 470 feet, wider than today's, plus more land at the interchanges and the flyover to Loop 363. Your exact strip is shown on TxDOT's roll plots, which are linked in the sources below. Being close to the road does not by itself mean a taking; the roll plots show who is affected.

When will TxDOT start buying land?

TxDOT's August 2026 timeline says land buying would begin in late 2027, after environmental clearance, and continue into summer 2028, with utility moves from 2028 to 2030 and construction starting in 2031. TxDOT says this depends on the environmental process and funding. Project Tracker expects the main job to bid in Jan 2031. As of October 27, 2026, TxDOT's public right-of-way parcel map shows no parcels being bought yet on the Segment 1 jobs.

What changed at the August 2026 meetings?

After owners and the community raised concerns at the January 2026 meetings, TxDOT cut the express lanes from six to four (one fewer each way). That narrowed the typical road strip from about 500 feet to about 470 feet and, by TxDOT's estimate, cut the land needed by about 26 acres, nearly 15%. TxDOT also lowered the design speed on the flyover to Loop 363 so it can use a tighter curve with fewer impacts on the neighborhood next to it.

Can I still comment?

The comment period for the August 2026 meetings closed on August 21, 2026. A formal public hearing comes before environmental clearance; TxDOT had not announced a date as of October 27, 2026. You can still contact the Waco District at (254) 867-2700, and what you tell TxDOT's right-of-way staff later still matters.

My business is on the I-35 frontage road. What should I watch for?

On a busy interstate the land under the strip is often the smaller number. Lost parking, a sign that has to move, a driveway that closes or moves, and a change in how customers reach you can cost far more. Those are damages and cure costs, and they have to be documented with how the property works today.

Do I have to accept TxDOT's offer?

No. Texas law requires TxDOT to make a written initial offer, give you the Landowner's Bill of Rights, and wait at least 30 days before a final offer, which must be at least the amount of its own written appraisal. You then have at least 14 days to respond. Those offers are TxDOT's opening position, not the last word on what your property is worth.

Is National ROW a law firm?

No. National ROW is a right-of-way and condemnation consulting firm, and we represent property owners only, never the agency. We do the valuation and negotiation work. When a case needs a lawyer, we say so and coordinate with condemnation counsel.

What does it cost to have you look at my offer?

The review is free. If you engage us, we work on contingency: our fee is a percentage of the increase above the original offer. If we do not improve it, you owe us nothing.

Where can I see TxDOT's drawings?

TxDOT posted the fact sheet, presentation, exhibit boards, environmental constraints map and 24 roll plots from the August 2026 meetings on its I-14 Extension page. The links are in the sources below. Roll plots 1 to 12 show the road strip block by block.

Send us what they sent you.

A TxDOT letter, survey request, appraisal or offer — whatever stage you are at, we will read it and tell you where it is weak. Free, and there is no obligation to go further.

Free review by a senior consultant →

Or call or text (469) 484-7960 — we answer owners the same day.

Sources

  1. TxDOT — I-14 Extension Segment 1 public meeting #3, August 5–6, 2026 (notice, fact sheet, presentation with script, exhibit boards, environmental constraints, roll plots 1–24).
  2. TxDOT — Segment 1 presentation with script (PDF), August 2026 (design changes, road strip width, land and construction timeline).
  3. TxDOT — I-14 Extension Segment 1 project page.
  4. TxDOT — Segment 1 public meeting #2, January 13–14, 2026.
  5. TxDOT — Project Tracker, 0015-14-109 and the related jobs linked in the table above, pulled October 27, 2026.
  6. TxDOT — right-of-way parcel map (ROW_ODP_Proposed_Parcels), TxDOT Open Data, checked October 27, 2026.
  7. TxDOT — I-14 System in Texas.
  8. Texas Landowner’s Bill of Rights — Office of the Texas Attorney General.

Related